KanREN Backbone - 02/29/08

February 21st, 2008

KanREN Staff will complete maintenance:

When: Friday, February 29th at 23:00 until Saturday, March 1st at 00:30

Duration: 90 minutes

Affected:
All KanREN backbone services will be impacted.

Impact:
Intermittent service outages as we re-provision the Foundry NetIron backbone routers.

Details:
When the current KanREN backbone was originally built we had intended to have two separate networks flowing over the same infrastructure; one for commodity Internet service and one for I2, KanREN sites, and other privately peered networks. This separation became less of an issue once the backbone was rolled out and the “Everything Else” network was dropped.

In order to enable advanced MPLS features, KanREN needs to remove the point-to-point VLANS from the backbone. This will require ~10mins of work in each NetIron. Thanks to the redundant links around the ring any service impact will be minimal. Only the kr-wsu <-> kr-esu link will experience any had downtime (approximately 5mins while the router reboots).

The tentative Schedule is as follows:
kr-wsu <-> kr-esu == 23:00 (reload required on ESU end)
kr-fhsu <-> kr-ksu == 23:10
kr-fhsu <-> kr-wsu == 23:20
kr-wsu <-> kr-psu == 23:30
kr-psu <-> kr-bryant == 23:40
kr-bryant <-> kr-kumc == 23:50
kr-ku <-> kr-ksu == 00:00
General clean-up == 00:10 - 00:30 (if needed)

Please Note: We will NOT be working on the kr-ku <-> kr-kumc backbone segment due to added complexity and additional transport VLANs.

If we’re ahead of schedule the times might fluctuate a little. Of course, if we hit an unplanned snag we’ll abort the window.

This window will NOT impact how each university connects to KanREN, only how our backbone ring devices connect with one another.

For those wanting to know how the backbone currently “looks”, check out the diagrams found here:
http://www.kanren.net/network/maps.html

If you have questions or comments regarding this maintenance window please contact the NOC at 866-984-3662.

Cox - 11/26, 11/27, 11/28

November 14th, 2007

Cox Communications will complete maintenance:

When:
Monday, November 26 from 00:00 until 06:00
Tuesday, November 27 from 00:00 until 06:00
Wednesday, November 28 from 00:00 until 06:00**

** Contingency day if needed

Duration:
6 hours each morning

Circuits Affected:
Baker - Topeka
Baker - Wichita
Barton CCC
Cowley College - Ark City
Cowley College - Mulvane
Cowley College - Southside
Frontenac HS
Garden City CC
Hesston College
Pittsburg USD 250

Impact:
Up to 15mins of total downtime during each window

Details:
Cox is performing routine maintenance on their Juniper core. This maintenance requires a reload of the hardware; thus the downtime.

If you have questions or comments regarding the maintenance windows described in this notification, please contact the NOC at 866-984-3662.

Cox (Cowley) - 11/12

October 30th, 2007

Cox Communication will complete maintenance:

When: Monday, November 12th from 00:00 until 06:00

Duration: 6 hours

Sites Affected:
Cowley College (Arkansas City)

Impact:
20mins total downtime

Details:
Cox is doing some fiber splicing in the area in order to provider greater capacity. They expect maximum downtime to be 20mins.

If you have questions or concerns regarding this maintenance window, please contact the NOC at 866-984-3662.

Cox (Cowley) - 11/15

October 30th, 2007

Cox Communication will complete maintenance:

When: Thursday, Novemeber 15th from 00:00 until 03:00

Duration: 3 hours

Sites Affected:
Cowley College (Arkansas City Campus)

Impact:
Approximately 5mins of downtime

Details:
Cox needs to re-sync the timing on one of their ONS cards. This process can result in ~50ms of downtime on the link. If OSPF is trying to update during that period, it may take a couple minutes to rebuild neighbors and complete the “flooding” process.

If you have questions or comments regarding this maintenance window, please contact the NOC at 866-984-3662.

Backbone - 11/05 and 11/06

October 22nd, 2007

KanREN staff will complete maintenance:

When:
Tuesday, November 5th from 00:00 until 00:30
Wednesday, November 6th from 00:00 until 01:00

Duration:
30 minutes Tuesday morning
1 hour Wednesday morning

Devices Affected:
ALL Foundry XMR backbone routers

Impact:
Device offline during reload and routing protocol rebuild

Details:
KanREN needs to perform a number of updates and configuration changes as part of this maintenance window. We are:
1) Upgrading software from 3.3.0 to 3.5
2) Changing TCAM profiles to allow for more route entries now that the I1 VRF is not being used
3) Enabling enhanced QoS features

The plan is to perform the changes on kr-ku the first night/morning and evaluate the process. If everything goes well, we will perform the changes and upgrade on all the other backbone routers Wednesday morning. Here is a preliminary schedule:
—-Tuesday
1) University of Kansas
—-Wednesday
2) 1102 Grand / Bryant Building [KC]
3) Wichita State University
4) Emporia State University
5) Pittsburg State University
6) KU Medical Center
7) Fort Hays State University
8) Kansas State University

We plan to perform all updates on the second night in 1 hour. The plan thus far is to not break the ring in more than one place at a time so connectivity to external networks should remain as stable as possible. Please note that Wednesday morning’s work does involve reload both routers that handle connections to Cox, Cogent, and the Great Plains Network (I2). While the routers will be fully reloaded by that time, our route advertisements will likely get damped by external networks. In other words: connectivity may take until 01:00 to fully stabilize in relation to Wednesday morning’s maintenance.

Cox - 10/26 and 10/27

October 19th, 2007

Cox Communications will complete maintenance:

When:
Friday, October 26th from 00:00 until 06:00
Saturday, October 27th from 00:00 until 06:00

Duration:
6 hours each morning

Sites Affected:
Barton County Community College
Cowley College - Ark City
Cowley College - Mulvane
Cowley College - SouthSide
Frontenac High School
Hesston College

Impact:
One 5 minute outage during each window.

Details:
No additional details are known regarding this maintenance window.

If you have questions or comments regarding this maintenance window please contact the NOC 866-984-3662.

Cox (FHSU) - 10/25/07

October 19th, 2007

Cox Communications will complete maintenance:

When: Thursday, October 25th from 00:00 until 06:00

Duration: 6 hours

Sites/Circuits Impacted:
Fort Hays State University Backbone Circuits
Garden City Community College

Impact:
One 10 minute outage

Details:
No additional details are known for this maintenance window.

If you have questions or comments regarding this maintenance window please contact the NOC at 866-984-3662.

Cox PON Sites - 10/12

October 8th, 2007

Cox Communication will complete maintenance:

When: Friday, October 12th from 00:00 until 06:00

Duration: 6 hours

Sites Affected:
Cowley College - Mulvane
Frontenac HS
Pittsburg USD250

Impact: 5 min outage toward the beginning of the window (exact time undetermined).

If you have questions or concerns regarding this maintenance window please contact the NOC at 866-984-3662.

kr-ku reboot 10-03-07

October 1st, 2007

KanREN staff will complete maintenance:

When: Wednesday, October, 3rd from 06:30 until 06:45

Duration: 15 minutes

Sites Affected:
University of Kansas
VLAN 205 - KU<->KUMC
KU Endowment
Lawrence Public Library
KanREN NOC

Services Affected:
KanREN Hosting Services (Plesk server)
Webhosting on Chloe
TACACS Logins to Site Routers
DNS Resolution on NIC (Primary)
Media Streaming on Helix
Marratech Server

Impact:
Sites and Services unavailable

Details:
The Foundry NetIron XMR 4000 router at KU (kr-ku) needs to be rebooted to remove some portions of configuration remaining from the former OC-12 to GPN. Expected downtime is only 3-5mins (the NetIrons boot extremely quickly).

This outage will NOT impact Internet2 or commodity Internet services.

If you have questions or comments regarding this maintenance window please contact the NOC at 866-984-3662.

chloe databases - 08/19/07 (updated)

August 17th, 2007

The maintenance described below was completed successfully. If you are experiencing any problems with the services impacted, please contact the NOC at 866-984-3662. –BF

——————————————-

KanREN Staff will complete maintenance:

When: Sunday, August 19th from 00:00 until 01:00

Duration: 1 hour

Services Affect:
Database services on chloe.kanren.net (old KanREN hosting server)

Impact:
Any blogs or databases hosted on chloe will be unavailable during the window.

Details:
We need to perform steps to recover passwords on the MySQL database running on Chloe. I only expect the process to take 10 minutes or less but have scheduled an hour in the event something goes wrong.

If you have questions, comments, or concerns regarding this maintenance please contact the NOC at 866-984-3662.